Nawalpur (Nawalparasi). Dubo planting has been started on the divider in the middle of the Narayanghat-Butwal road, which has been extended to four lanes. The work of planting dubo in the three-meter wide divider between the roads of about 113 km length is being done rapidly.

According to Engineer Shiv Khanal, Information Officer of Narayanghat Butwal Road Extension Plan Eastern Section, the work is being done on the dividers between the roads in Gandakot, Devchuli, Kawasoti and other places. He said that under the road widening plan, the black sheeting work is almost completed, he informed that now the work is being done on the roadside service lane, painting on the roadside dividers and planting trees on the middle divider and planting trees to make the road look beautiful.

The East-West Highway, which was started in 2018 by the then King Mahendra Shah at Gaandakot in Nawalpur, has been expanded to four lanes after about 65 years. Narayanghat Butwal road expansion contract was signed from January 2075. After the foundation stone of the road was laid in March of the same year, the expansion work started. According to Information Officer Khanal, the road expansion work which started within 42 months from the date of the agreement was extended four times at different times and was completed in July last year.

“We have completed the takeover of the road in July, after the road is almost completed, the road has only been taken over, the handover has not taken place. After the road takeover, the construction company works to correct the errors for five years. Only then is the handover done”, said information officer Khanal. He said that during the construction of the road, there will be a trial period in which the construction company will have to repair the road for five years, as various defects of the road cannot be detected.

After the completion of the main work of blacking and slope of the road, now the work is being done to correct the error, prepare a box for pedestrians, put railings on the side of the road, and slope. Both parts of the contract, divided into two parts, were done by the Chinese construction company “China State Construction Engineering Corporation” through global tender. About 17 billion rupees budget has been spent for the expansion of the road, which was divided into the eastern section (65 km) from Gandakot to Daunne and the western section (48 km) from Daunne to Butwal.

85 percent of the total budget has been provided by Asian Development Bank (ADB) as a loan at 1.5 percent interest rate. As part of the 113 km road extension of Narayanghat-Butwal, 70 km of four lanes, 29 km of six lanes (with four lanes and additional service lanes on both sides) and three lanes of 14 km of Downe have been constructed. Thus, according to the project, the design of the road has been made differently according to the geographical and transportation needs of the market area, flat terrain and hilly areas.

The road which has been expanded to four lanes in rural areas and forest areas has been expanded to six lanes in urban areas, while the road has been expanded to three lanes in areas with geographical difficulties. In addition to this, arrangements have been made to use speed guns for lane marking, traffic signals, speed limit signals and surveillance on the roads. Information officer Khanal informed that the speed limit has been set to reduce accidents as the speed of vehicles will increase after the road expansion.

According to Information Officer Khanal, the maximum speed limit on straight and open roads is 80 km per hour, the maximum speed limit is 60 km per hour in market areas and crossing areas, and the maximum speed limit is 40 km per hour in forested areas and hilly areas. In the hills of Downe area, the black-paved road has deteriorated and washed away several times, so cement concrete has been laid in about 11 km area. 49 thousand 830 trees were cut for the expansion of about 113 km road from Gandakot to Butwal.

Along with the expansion of the road into four lanes, 21 big bridges, 43 small bridges and 46 culverts (drains) have been constructed in this area to drain the water from the road. During road expansion, small bridges and culverts have been prepared in four lanes, while large bridges have been prepared in two lanes to the south of the old bridge. According to information officer Khanal, the old bridges were upgraded and replaced according to the requirements and technical conditions.