Chitwan. At Ghoptevir on the Muglin-Naubise road section of the Prithvi Highway, traffic has been stopped and the dangerous part has been cleared. Starting from Saturday afternoon, traffic has been stopped for five hours every day and the dangerous part has been removed.

According to Sachendra Mishra, Information Officer of Nagadhunga-Muglin Road Project (West Section), a road was made from Nagadhunga side and an excavator was taken to the upper part of Ghoptevir on Saturday. The excavator has started cutting the dangerous and collapsing mound of the hill from today.

According to Ishwar Nepal, engineer of the construction company Sharma ZICG JV, the excavator has been brought to a place about 100 meters high and the hill has been cut. He informed that work was done by stopping vehicles on the road from 11:00 am to 4:00 pm. He said that the excavator will be lowered by cutting the hill in layers.

“If it is seen that more equipment or excavators can be taken to the hill, there is a plan to add another excavator by Monday. Since traffic is stopped, the road has been expanded by cutting the wall towards Muglin of Ghoptevir. Here, about three meters should be widened in the 150-meter long section”, said Nepal.

According to Nepal, widening of the road has started in the Dahaki river between Chumlingtar and Kurintar. “The road has to be widened by two meters in a 100 meter long area. Two excavators and a loader have been used to cut the wall in both places”, he said.

Chief District Officer Ganesh Aryal said that the construction company has been stopped by stopping the vehicles to complete the work within five days. He says that the dangerous part of Ghoptevir is going to be removed by making necessary facilitations from the government. He informed that they were also asked to work at the places where the road needs to be widened during the traffic stop.

For almost a month now, there has been a problem in the traffic in Ghoptevir due to the dry landslides. Landslides have stopped the traffic several times, and one person has also died due to falling stones. Ghoptevir is about three kilometers from Muglin towards Kathmandu. This road is used to enter and exit the capital. More than 1,500 vehicles travel on this road in a day.