Sankhuvasabha. More than 50 percent of the construction work of the 47.1 MW capacity Gurans Hydro Project under construction in Sankhuwasabha and Bhojpur districts has been completed. The project, which is estimated to cost around 8 billion 20 million rupees, is accelerating the construction.
The headworks of the project, which is being constructed using the water of the Sankhuwa river, is being constructed in the area of Barhaba under Salpasilichong Rural Municipality-1, 2 and 3 of Sankhuwa Sabha. A dam has been constructed at the confluence of Sankhuwa and Sisuwa rivers and a project structure has been prepared to deliver water to the power plant through a 6,400-meter long tunnel.
The power house of the project is being constructed in Bekhuwa area under Salpasilichho rural municipality-1 and 2 of Bhojpur. According to the project, the structure has been built to release the generated electricity into the Arun River.
Meanwhile, 422 families in the project-affected areas have been awarded founder shares. Shares have been provided to the affected families from a minimum of Rs 1 lakh to a maximum of Rs 5 lakh.

Shivprasad Ghimire, executive chairman of Gurans Hydro Limited, handed over share certificates to the affected families at the event. In the program, he said that the project is important for the development of the country’s energy along with the development of the local area. He said that the support and cooperation of local residents and stakeholders is important in the construction of the project.
About 700 people including technicians, construction workers, security personnel, Nepal Police and Nepali Army are currently involved in the construction of the project. According to the project, besides creating jobs at the local level, the construction work has also increased economic activity.
More than 50 percent of the construction of the project has been completed, and the work has been accelerated in the coming days to achieve the goal of electricity generation. After the project is operational, it is expected to contribute to the local economy of Sankhuwasabha and Bhojpur, energy development and national electricity production.