Kathmandu. It has been seven years since the construction of the Parliament building started in the Singhdarbar complex. During this period, the deadline has been extended up to 6 times. But the work is not over yet. Although the government is preparing to conduct the next winter session from the new assembly hall, it is not certain. But government officials are claiming that the winter session of the parliament will be held in the new assembly hall. The special building construction project has said that the chamber of the House of Representatives of the new parliament building has been prepared.
The work of technical testing in the meeting room remains. Roshan Shrestha, the head of the special building construction project, said that for the time being, only the House of Representatives room was used. “The work of the House of Representatives has been completed, the work of the National Assembly still remains,” he said. The overall construction work has been completed. He says that only the finishing i.e. interior work is left.
“The work did not go well during Dasain-Tihar, although some of the interior items had to be brought from China, there was a problem due to the closure of the border,” Chief Shrestha said. But the Federal Parliament Secretariat says that it is difficult to conduct the meeting due to its narrowness.
Ekram Giri, Joint Secretary and Spokesperson of the Federal Parliament Secretariat, said that despite the information that the House of Representatives chamber has been prepared, the technical aspects have yet to be tested there. When the meeting of the Assembly is going on, it will be broadcasted live. For that, we have to test the audio and video conference system,’ he said, ‘We have to see if there is a problem or not.’ The technical test could not be done because the meeting room was not ready and handed over.
As the Assembly Chamber has not been handed over to the Parliament Secretariat, the Parliament Secretariat is not sure that the winter session will be conducted here. Giri says that the goal is to conduct the winter session from the new room. “But work is still being done at the entrance to the assembly hall, so it seems that it will take time to complete the work of the entire parliament building,” Giri said, “The parliament secretariat is ready to hold the meeting from the second week of November.”
The contract for the construction of the Parliament building was placed on 16 October 2076 with the aim of holding the meeting of the House of Representatives to be formed from the 2079 election. But since the building was not ready by the time the new House of Representatives was formed after the election of 2082, the multi-purpose hall was hastily held and the meeting was conducted. The National Assembly meeting has also been conducted in the old hall of the Agriculture Committee as the new assembly hall is not ready.
There are four committees under the National Assembly, 10 under the House of Representatives and two joint committees. At present, there was a problem in holding committee meetings as the hall was not sufficient. Tundi-Sec JV has taken the contract to complete the construction of the Parliament building at a cost of 5.67 billion 2.7 million rupees. The initial deadline was till 16 October 2079. After the work was not completed, the deadline was extended for the first time till 30 Chait 2079. The deadline was extended for the second time up to 19 October 2080, the third time up to 19 March 2080, the fourth time up to 18 March 2081 and the fifth time up to 16 December 2082. Since the work could not be completed this time, the deadline has been extended until next February.
The contract for ‘interior’ was taken by KC-Shyamsundar-Baniyan JV. Its contract amount is 2 billion 345 million. It was agreed on 17 June 2080 to be completed by June 2081. But the deadline was extended till 16 Chait 2081 as the work was not completed. After the work was not completed again, the deadline was extended for the second time till 16 January 2082. After the work was not completed during this period too, the deadline was extended for the third time till Baisakh 2083. Now the deadline has been extended for the fourth time till Baisakh 2084.
The parliament building has been constructed on an area of 156 ropanis in the Sinha Darbar complex. The new buildings are up to five stories high. The House of Representatives, the National Assembly Building, the Central Lobby, the office building of highly distinguished persons, a library and a museum are being prepared there. Parliamentary Party Office Building, Parliamentary Committee Building, Parliament Secretariat Building, Chamena House, Press and Printing House have been built separately. Infrastructure has been prepared for parking 476 four-wheelers and 800 two-wheelers. A building for security personnel has also been prepared.
A separate contract for ‘Roofing’ was taken by Chainlink Engineering Company for Rs 3 crore 79 lakh. Although the contract was signed on 27 February 2080, the work has not been completed yet. After the work was not completed, its deadline has also been extended till Baisakh 2084. According to Dilip Bhandari, Director General of Urban Development and Building Construction Department, instructions have been given by Speaker Dol Prasad Aryal to prepare the House of Representatives chamber for conducting the winter session and the construction work has also been accelerated.
“The plan is to complete all the building work by next month,” said Bhandari. “At present, along with the interior work, the security system is also being worked on.”