Kaski. Under the Nepal Electricity Authority’s Pokhara-Bharatpur distribution system strengthening project, 82 percent physical progress has been made in Pokhara and 95 percent in Bharatpur.
Project chief engineer Anand Subedi informed that under the project started by the authority four years ago with the aim of laying electric wires underground, the target is to complete the work in Pokhara by next month and in Bharatpur by next month. According to him, the work of Bharatpur has reached its final stage.
In Pokhara, there is a plan to lay electrical wires underground in a total area of 223 km, so far, wires have been laid in an area of 165.7 km. Engineer Subedi said that 55.2 km of that area has already received electricity from the underground system. In the first phase, the authority is working by prioritizing the main urban areas of Pokhara and places with high tourist traffic.
Pokhara Metropolitan City-14 from Chowthe to Kundahar, Amarsinghchowk, Buddhachowk and Setipul, more than 400 households in the Prithvi Highway area have been provided electricity service through the underground system. Similarly, he informed that the wire laying work has also been completed on the main road connecting Lakeside through Setipul, Prithvi Chowk, Bhawan Chowk, Srijan Chowk, Zero Kilometer.
Even the inner roads of Lakeside have been wired and now only electricity remains. Currently, wiring is being done on some sections of the road connecting from Bhawan Chowk to New Road to Chipledhunga and from Srijan Chowk to Nagadhunga to Talbarahi Temple at Lakeside.
“Since the Seti Bridge is under construction, electricity cannot be supplied immediately to the wire laid towards Prithvi Chowk”, Engineer Subedi said, “As the construction of the bridge has reached its final stage, the electricity service will be operated from the underground system in the rest of the area soon.”
As part of the project, along with the main highway of Pokhara, underground wiring is also being done on the subsidiary roads. Along with electric wires, optical fibers have also been laid for telephone, cable television and internet services. According to the project office, the old electrical poles and wires have been removed in the area where the underground system is in operation. The goal is to provide electricity service to 6,000 households in Pokhara through an underground system.
Similarly, in Bharatpur, there are plans to lay electric wires underground in a total area of 156.33 km, so far 155.37 km of wires have been laid. Engineer Subedi informed that 137.87 km area has been supplied with electricity. The goal is to provide electricity service to 1,200 households in Bharatpur through an underground system.
It is expected that by removing unorganized and dilapidated electric poles and undergrounding the wires, the urban beauty will be maintained and the risk of accidents will also be reduced.
In January 2022, the Indian company Tata Projects got the construction contract for the project. With the help of concessional loan of about three billion rupees from the Asian Development Bank, the authority has conducted distribution system strengthening projects in Pokhara and Bharatpur.