Myagdi. Water supply has been resumed in the Beni market of Myagdi, which has been affected for one and a half months after the flood damaged the main water pipeline.

Beni Drinking Water and Sanitation Consumer Organization has started supplying water to Beni market by constructing a temporary pipeline from Rithakhark and Dandakhark springs located in Annapurna Rural Municipality-8.

Ramesh Giri, president of the organization, informed that after repairing the main pipeline which is about 14 km long, the water operation test was successful from Tuesday evening. According to him, it has been tested that water can be supplied at the rate of eight liters per second.

Temporary and alternative pipelines have been constructed in Rahupare-Galeshwar and Dallepipal-Beni sections. Chairman Giri said that after landslides started in Khoria and Khareni in Beni, the route of the pipeline had to be changed and a new pipeline had to be extended for about three kilometers in Dallepipal-Kalipul-Beni circular path-Darwang bus park area.

After the disaster, three liters of water per second were brought from Kopre’s spring, 3.4 liters from alternative Amreni spring and four liters from Rahupare and distributed in Alopalo system. According to the organization, after the alternative spring started drying up, water supply was started again from Rithakhark and Dandakhark springs.

According to the vice president of the organization, Rajendra Shrestha, more than 20 liters of water is needed per second in Beni market. Through the organization, drinking water has been distributed to about 25,000 people living in 1,200 households of Ward No. 2, 7 and 8 of Beni Municipality.

The pipeline bringing water from Dandakhark and Rithakhark springs, which can supply 22 to 25 liters of water per second, was blocked after the disaster. Keshav Prasad Regmi, secretary of the organization said that preparations are being made to bring water from Rahupare before Tihar by extending a temporary pipeline along the Beni-Jomsom road as no other option is immediately available.

According to him, a proposal has been submitted to the Water Supply and Sewerage Management Department with a cost estimate of Rs.