Kathmandu. The devastating flood that occurred on Rasuwa-Bhotekoshi river on 10th of August last year caused a loss of 1 trillion 32 billion 83 million rupees in the energy sector. The preliminary report of the Post Disaster Needs Assessment (PDNA) released by the National Planning Commission has shown that the power sector has suffered a lot from the floods.
According to the report, the flood caused a loss of 4 trillion 72 billion 66 million rupees to the entire economy. It is estimated that 2 trillion 18 billion 58 million rupees will be required for the revival and reconstruction of the energy sector alone.
According to the report, there was a loss of 89.26 billion rupees in the public and private sector due to the flood and a loss of 43.56 billion rupees. The commission has estimated that there is a loss of Rs 82 billion 79 crore and a loss of Rs 50 billion 3 crore towards the public sector alone.
The flood damaged 14 hydropower projects in Rasuwa and Nuwakot. Among the damaged projects, seven belong to the private sector and seven belong to the Nepal Electricity Authority and its subsidiaries. Similarly, 6 substations, transmission lines, distribution lines and electric poles have also been damaged.
The 111 MW Rasuwagadhi, 120 MW Rasuwa Bhotekoshi, 216 MW Upper Trishuli-1, 60 MW Upper Trishuli-3A, 20 MW Langtang Khola, 14.1 MW Devighat, 24 MW Trishuli, 22 MW Chilime and 100 MW Super Trishuli projects were damaged by the flood.
Similarly, five megawatt Mailung river, 15.625 megawatt central Trishuli Ganga, 37 megawatt upper Trishuli-3B, 14.3 megawatt upper Mailung and five solar power projects with a capacity of 24.36 megawatts were also affected by the flood.