Sanja. The buildings of Ayurvedic dispensaries, which were started at three local levels in Syangja with the aim of providing Ayurvedic health services to the locals, have not been completed even after 6 years. In Andhikhola Rural Municipality-5 Setidobhan, Arjunchoupari Rural Municipality-5 Aruchour and Walling Municipality-1 Dhanubaanse, the buildings under construction are like abandoned buildings.
The building, which was started 6 years ago after the agreement, has not been completed yet. According to the agreement, the work on the buildings of Setidovan and Aruchour, which was supposed to be completed in two years, has been completed only about half. The expected progress has not been made even in the Dhanubase building, which was contracted to be completed in one and a half years. Locals allege that the construction of infrastructure in sensitive areas like health has been affected due to the slowness and negligence of construction workers.
Valley/Baburatna JV Lalitpur signed an agreement on 11th February 2077 for the construction of Ayurveda dispensaries in Setidovan and Aruchaur. Similarly, engineer Yogendra Bastakoti informed that Safe Engineering Builders Pvt Ltd Chitwan has signed an agreement with Federal Project Implementation Unit Pokhara under Federal Urban Development and Building Construction Department on 19th February 2077 for the construction of Ayurveda Dispensary in Kharedhanubanse.
According to Bastakoti, an agreement was signed for the construction of primary health center building in Setidovan for Rs.
About six years after the agreement, only 65 percent material progress has been made in Setidovan and 50 percent in Aruchaur. The financial progress of both projects is 44 percent. Although the slope and plaster work of the building has been completed, other works are still pending.
Similarly, for the construction of the building of Ayurveda dispensary located at Walling-1 Dhanubase, an agreement was signed for 1 crore 79 lakh 12 thousand 470 rupees. However, even after the deadline, only half of the work was done, said engineer Laxman Lamsal.
Lamsal says that although the office has corresponded several times to advance the construction work, the construction company has not made the expected progress. He informed that the office has also issued a notice to terminate the contract after the work was not completed within the specified time. It is said that the construction company has not worked in Dhanubase for the last one and a half years.
The delay in the construction of the building has also affected the health services available to the locals. According to Hari Prasad Aryal, head of Dhanubase Ayurveda Pharmacy, the dispensary has been providing only general health check-up, medication and consultation services from a rented house.
Aryal said that services such as medical yoga, Shirodhara and manufacturing of Ayurvedic medicines could not be conducted due to lack of buildings and necessary infrastructure. He said that the lack of buildings has hindered the expansion and effectiveness of dispensary services.
Although there has been some construction activity in Setidovan and Aruchaur recently, work has been stopped in Dhanubase for a long time. All the three buildings were not constructed on time, and the Ayurvedic health services that the locals should get have been affected. It is seen that until the construction of the building is completed, the dispensaries will have to provide limited services from rented houses.