Chitwan. It will take three more days to stop the traffic at Ghoptevir on the Muglin-Naubise road section of the Prithvi Highway and remove the dangerous part.

According to Sachendra Mishra, Information Officer of Nagadhunga-Muglin Road Project (West Section), it took more time because it was difficult to work due to difficult geography.

Since last Saturday afternoon, traffic has been stopped for five hours every day, and work is being done to remove dangerous parts. He said, “If there are no more problems, the goal is to be able to work in the next three days.”

Excavators are working to remove dangerous parts from above and clean the road from below. Every day from 11:00 a.m. to 4:00 p.m. vehicles have been stopped.

According to Ishwar Nepal, an engineer of the construction company, the machine is being taken to the hill about 100 meters above the road and the cutting work is now being done. He said, “Progress has been slow because it is a very risky job.”

Only on Tuesday, the upper mound fell and the excavator reached. He informed that after removing the landslide, the excavator is working again. He said that preparations are being made to send one more machine up the mountain until it is met.

Similarly, at the time of road closure, widening of the road has also been started in the Dahaki river between Chumlingtar and Kurintar. As the road has to be widened by two meters in the 100 meter long area, the wall has been cut using a excavator and a loader in both places.