Chitwan. The fourth edition of Nepal Premier League (NPL) can be held at Gautam Buddha Cricket Stadium under construction in Bharatpur. As the infrastructure work of the stadium has reached its final stage, if the work of connecting the ‘floored light’ can proceed, then the NPL will be able to be played almost a year later.
On the day the third edition of NPL ended, Prime Minister Walendra Shah has already announced that eight cricket clubs will conduct the tournament on the ‘home and away’ system. Along with this, Infrastructure Development Minister Sunil Lamsal has discussed this matter with the owners of all eight clubs on Tuesday. Ayus Neupane, president of Chitwan Rhinos, who participated in the discussion, said that he was optimistic that the fourth NPL would be held in Chitwan as the infrastructure development minister was very positive. He said, “During the discussion with the minister, there was a discussion about whether the games can be played in Chitwan and Mulpani next year.”
He said that since the construction work of the stadium will be completed in a few months, if the federal government does the flooring and technical works, there will be no problem in playing the games.
President Neupane says that Chitwan is close and convenient for the clubs of Janakpur, Lumbini, and Pokhara. Prime Minister Shah has designated Chitwan Rhinos’ home stadium as Gautam Buddha Stadium.
Chitrasen Adhikari, Acting Chief of Bharatpur Metropolitan City, says that the infrastructure work of the stadium will be completed within the next four months. According to him, 68 percent of the stadium work has been completed. The work of both ‘Tower Structures’ is integrated. Finishing work is going on. After the work of the sitting area of the parapit is completed, preparations are being made for the slope behind the parapit. Acting Chief Officer says that 80 percent of the parapit has been completed.
He said that the work of laying the drainage pipe of the sub-surface of the ground has started and then the pitch work will be continued by placing ballast. Drainage and compound work has been completed. According to him, 15,000 people will be able to sit and watch cricket when the first phase of this work is completed. The second phase is planned to work gradually. When the second phase of work is completed, a stadium with a capacity of 30,000 people will be built.
An agreement was signed between Dhurmus-Suntali Foundation and Bharatpur Metropolitan Corporation on 16th January 2075 and the preliminary work started from November 2076. Since the foundation could not raise financial resources, the construction was stopped from 2078. After the Foundation handed over the ownership to the Metropolitan Corporation, Bharatpur Metropolitan Corporation awarded the contract to Himalayan JV on 24th June 2081 for the first phase of the stadium. The date of the 30-month contract is expiring on 27th of January. The Acting Chief Officer estimates that he will be able to work in two more months.
The initial contract amount was Rs 785 million 91 thousand, but now it has increased to Rs 86 million 24 million 84 thousand. The Acting Chief Officer said that to complete the work of the second phase, apart from the floor light, it is estimated to cost around two billion rupees for civil works. He said, “If the federal government provides more infrastructure and floor lights, the next NPL can be played like this.” He said that it is a suitable place in terms of geography and he said that the games of neighboring countries India and Pakistan can also be played in this way.
Anil Adhikari, Director of Cricket of Bagmati Province, said that the fourth edition of the NPL should be held in Bharatpur. He says that he is confident that the fourth edition will be the same as the government itself is positive. Stating that the capacity of the Trivi Cricket Stadium is only 10,000, he said that when the first phase of the work is completed, it is suitable because it can accommodate 15,000 and later 30,000 spectators. He said, “We were able to install seats and floor lights in Trivi Stadium in nine months, here we have 11 months, why can’t we?” The official said that national and international games can be played here. There are seven pitches in Trivi, while five pitches can be made here.
Officials say that Bharatpur is suitable for athletes from the Terai district. Secretary of Chitwan District Cricket Association, Suraj Gyawali, said that since the stadium has been built according to the standards, everyone’s support and cooperation is needed to hold the fourth edition of NPL here. He said, “We are sure that the fourth edition of NPL can be done here, because the government is positive.”
He said that the matches of some clubs in neighboring districts can be played here. From Bharatpur, Chitwan is easy for clubs like Pokhara, Lumbini, Janakpur. Hotels are comfortable for players and spectators to stay, while Chitwan National Park and other tourist spots are located in the district for sightseeing when there is no match.