Dhulikhel The Japan International Cooperation Agency (JICA) has started the reconstruction work on the Sindhuli Barkhekhola-Piple road section of the BP highway damaged by natural disasters. Along with that section, the reconstruction has been accelerated in other three sections according to the Divisional Road Office, Bhaktapur.
According to the office, for the reconstruction of the Barkhekhola-Pipley road section, the work has started after signing an agreement with JICA for 2 billion 600 million. Division Head Suman Yogesh informed that JICA has started work recently.
Similarly, 52 percent physical progress has been made so far in the reconstruction work in the section from Pipley to Bhakundebensi in Kavre. According to him, Khani-Awan-Kamaljit JV, which has been entrusted with the reconstruction from Dalabensi to Charsaybensi (8.5 km), has said that it will complete the construction work by the end of May 2084.
Similarly, Yogshe said that the road from Charsaybensi to Bhakundebensi (11.8 km) Lama-Nawakantipur JV has started the process to complete the work by June 17, 2084.
Similarly, Uma & Company-Bhandari JV, which has been entrusted with the Piple to Dalobensi (2.3 km) road section, will be able to construct it by October 26, 2084. According to him, the BP highway reconstruction work is being done according to the target.
In the second week of October 2081, 29 km of road from Dapcakhola 1 bridge at Namobuddha to Nepalthok in Sindhuli was completely damaged due to the flood in Roshi river.
Among the damaged highways, the 25.11 km road towards Kavre is being reconstructed in three sections. Yogesh said that preparations are being made to cover one layer of black paper in the three sections under construction before the next rainy season. According to him, reconstruction is being done on the flood-damaged BP highway ‘dedicated double lane’.
Under the highway, an agreement has been signed with Uma & Company-Bhandari Amarjyoti JV for 688 million to rebuild the 2.3 km road from Piple to Dalabensi in Kavre, Lama-Nav Kantipur JV for 1.42 billion for the road from Dalabensi to Charsyabensi, and Khani-Awan-Kamaljit JV for 1.33 billion to reconstruct the road from Charsaybensi to Bhakundebensi.
Meanwhile, it has been reported that traffic on the BP highway is currently being rehabilitated. “Since it is narrow in a couple of places, two-way traffic has been made by creating diversions, there is no problem elsewhere,” said Yogesh.
According to him, due to steepness in Chowkidanda and Pinthali, they are currently being repaired and diverted. A similar arrangement has been made in the Dalabensi-Piple section. There is no traffic jam even though the road is currently being reconstructed. Material has been managed to open the road in half to a few hours if it rains and is taken from the road and blocked by landslides.
The highway is considered as a short route connecting the eastern and central hilly regions of Nepal with the federal capital Kathmandu. The government has approved a total of eight billion 500 million resources for the reconstruction of the damaged section. Three road sections towards Kavre have been given 7 billion 500 million and one road section of Sindhuli has been given resource consent of 1 billion.
According to Yogesh, there is a plan to convert five bridges into two lanes. 6.3 km of RCC wall will be constructed in all the three sections. The BP highway (Dhulikhel-Sindhuli-Bardibas 160 km road) was constructed from the financial year 2053/54 with the help of a grant from the Government of Japan. The highway, which was divided into sections and completed, was handed over to the Nepalese government on 18th June 2072 by the Japanese government.