Kanchanpur. So far, 26 percent of the dry port under construction at Dodhara Chandni has been completed.
The construction period of the much awaited dry port has been fixed for 30 months. The port will be built at a cost of around two billion 37 million Indian rupees.
Engineer Anish KC of Nepal Intermodal Transport Development Committee informed that the construction of the port has started from December 24, 2025. He expressed his belief that after the construction of the project, the economic activity in Far West will increase.
A Memorandum of Understanding was signed on June 1, 2023 between the Government of Nepal and the Government of India for the construction of a port in Gourishankar Community Forest located in Dodhara Chandni Municipality-1. According to the Inter-modal Transport Development Committee, two warehouse buildings, customs check building, quarantine building, immigration building, security building and other infrastructure will be built on the 42.36 hectares area used for the construction of the port.
A six-lane access road to the dry port towards Nepal and a four-lane concrete bridge over the Mahakali river have been put into operation. An access road to the port towards India is being constructed. With the construction of the dry port, it is expected that the door will be opened for the development of the Far West.