Mustang. The Leyte-Dhampu motorable bridge over Kaligandaki river connecting three wards of Thasang Rural Municipality of Mustang has not been completed even after seven years. Due to extreme delays in construction, the bridge has been stalled for the last 10 months.

Under the Ministry of Infrastructure Development of the Government of Gandaki Province, the bridge is being constructed through the Infrastructure Development Office Mustang and is going to be constructed to connect Ward No. 2, 3 and 5 of Thasang Rural Municipality.

The bridge will connect the villages of Dhappu, Sirkhum, Sauru, Titi, Kunjo and Taklung across the Kaligand along the Beni-Jomsom road to the rural road network. For the construction of the bridge, a contract was signed with Dev and Sayer Construction on 29th February 2076 for five million rupees. So far, the construction has not been completed even though the deadline has been extended five times.

According to Ravin Chokhyal, Head of Infrastructure Development Office, according to sub-rule 3 of Rule 120 (a) of Public Procurement Regulations, 2064, the latest deadline for bridge construction has been fixed until the end of June of the current financial year. He informed that 77 percent physical and 74 percent financial progress of the bridge has been achieved so far.

The length of the bridge under construction over Kaligandaki river is 35 meters and width is 8.4 meters including footpath. The construction company that got the contract has been doing the work through a subsidiary construction company (petty contractor).

Chief Chokhyal said that although the construction company has been repeatedly instructed to proceed with the work, the construction has stopped due to the neglect and delay of the representative of the sub-contractor. According to him, the meeting is being prepared to ensure the commitment to complete the construction by involving the representatives and stakeholders of the bridge construction company.

The work of the abutment on both sides of the bridge up to the cap level has been completed. Head of the office Chokhyal informed that the slab slope, approximate road, other structural works related to the bridge, finishing and auxiliary works are completed and the bridge is made operable and handed over.

The construction of the black paper road through the Divisional Road Office Baglung under the federal government has been completed to connect the villages across the river in Kaligand. Local Naveen Sherchan said that the delay in the construction of the bridge is unfortunate. He said that if the construction company had been careful, the construction of the bridge could have been completed four years earlier.

If the construction of the bridge is completed, it is expected that the residents of the three wards of Thasang Rural Municipality will be able to travel easily to the main highway, and it will help in the marketing of agricultural produce, development and promotion of tourism. Rasas