Kathmandu. The physical progress of construction of Kathmandu-Terai/Madhesh Expressway, a project of national pride, has reached about 51 percent. Under the project under the management of Nepali Army, the longest Mahadeotar tunnel has had a breakthrough on Wednesday.

President Ramchandra Paudel made the breakthrough of the 3,422-meter long Mahadeotar tunnel. The Nepali Army expects that the construction of the expressway tunnel will speed up with the connection of the excavated part of the tunnel from both sides.

According to the army, 14 tunnels are being constructed at seven locations on the expressway. Earlier, five tunnels in three places had breakthroughs. With the breakthrough of the Mahadeotar tunnel, it is believed that the tunnel construction work of the project will get more speed.

According to the army, the construction of the substructure of most of the structures of the project has been completed. Construction of high-tech bridges and other structures is also ongoing.

However, the land acquisition dispute in Lalitpur’s Khokna-Dumkisap area still remains a challenge. According to the army, efforts are being made to resolve the dispute of about 6.5 km road section in that area and after the problem is resolved, the contract will be managed and the construction will be started.

At the breakthrough program of the Mahadeotar tunnel, President Paudel expressed his belief that there will be a qualitative change in the transport system of the country after the construction of the expressway is completed. He said that the distance and travel time between Kathmandu and Terai/Madhesh will be reduced after the 73 km long modern expressway is operational.

President Paudel said that along with physical infrastructure development, the expressway will also contribute to social and economic transformation. He mentioned that this will reduce the geographical distance between the capital and the Terai/Madhesh and further strengthen social harmony, mutual tolerance and national unity.

According to him, after the expressway is operational, it will help in promoting tourism, facilitating trade and transportation, and expanding regional economic activities.

President Paudel mentioned that he had inspected the expressway for the third time and expressed his satisfaction with the progress achieved by the Nepali Army. He said that the efficiency and commitment shown by the army in building infrastructure despite the difficult geographical conditions, complex terrain and adverse conditions is commendable.

He also emphasized on the need for effective coordination between the government, the Nepali Army, construction professionals and other concerned agencies to complete the project on time.

Infrastructure Development Minister Sunil Lamsal, Chief of Army Staff, ambassadors of China and South Korea, government officials, consultants and representatives of construction industry were present in the program.

The Nepali Army has requested all the parties involved in the construction to proceed with the work at the same pace to complete the project on time.