Myagdi. The monsoon disaster has affected the power generation, transmission and construction of hydroelectric projects in Myagdi. The floods and landslides in the Kaligandaki and Myagdi rivers and their tributaries damaged the dams, power houses, tunnels, transmission lines and access roads of the projects that are in operation and under construction.

Due to the disaster, some projects have been completely closed, while the trial production and construction work of some have been affected. Due to the disruption in the transportation of construction materials and equipment to the project under construction, the pace of work has slowed down. This has increased the risk of increasing the cost of construction as well as prolonging the completion period of the project.

Erosion of the Kaligandaki river has washed away two towers in Annapurna rural municipality-1 Doba and one tower in Ratopani under the 220 kV capacity Kaligandaki corridor of Dana-Khurkot transmission line. A tower in Dhirchang has been partially damaged, while another tower in Tipplang area is at risk.

After the transmission line was blocked, there was a problem in connecting the electricity produced by the hydropower project in North Myagdi to the national system. According to Roshan Khadka, head of Nepal Electricity Authority’s grid office in Pokhara, a temporary tower was built in Bhirkate and electricity supply was resumed from last October 31st after pulling two kilometers of wires. The process of permanent reconstruction of the damaged tower and transmission line has been started.

Ghalemdikhola, Mristrikhola, Nilgiri-1, Nilgiri-2 and Relekhola of Annapurna Rural Municipality-4 Narchang as well as Thapakhola hydropower project of Mustang have been connected to the national system through this transmission line.

Two hydropower projects of Annapurna rural municipality have been closed due to floods. Homanath Pandey, the representative of the project, said that the Relekhola project with a capacity of six megawatts was closed after the flood from the Relekhark area deposited Gegran in the dam. Similarly, the 14 MW power plant of the Gharkhola project was buried by a landslide on July 26.

Then last October’s flood and landslide caused further damage to the dam. One person died and one person was injured when the power plant collapsed. Anil Tiwari, Head of Administration of Myagdi Hydropower, said that preparations are being made for the reconstruction of the project and according to preliminary estimates, the damage is more than one billion rupees.

The construction of the 180 MW Kaligandaki Gorge and the 66.3 MW Madhya Kaligandaki project under construction in the Kaligandaki basin has been affected for one and a half months. Krishnadas Shrestha, senior manager of the project, said that the work was stopped after the flood deposited Gegran at the dam construction site in Thapla, Ghasa, Mustang, Kaligand’s gorge.

Chandra Prasad Dhakal, Chairman of IME Group, Investor of Promoter Hydro Support Pvt Ltd said that the dam, tunnel, housing, machinery, equipment, construction materials, diesel tanker at Sukebagar of Madhya Kaligandaki project were damaged by flood. The flood destroyed the diversion of the construction site and damaged the residential buildings of Nagadhunga and Ratopani and the access road at Naulibagar.

The trial period of the 40 MW Rahughat hydropower project has been extended due to the damage caused by the erosion of the Kaligandaki river in the power house area of ​​Tilkenichour, Raghuganga Rural Municipality-3. The area near the tailrace gate and switchyard was damaged and the power house was flooded. Ganesh KC, managing director of the project, said that currently two units of 20/20 MW capacity are being operated alternately for trial production.

In the project under construction in the Myagdikhola basin, problems of access and transportation have also been seen. Jyotikumar KC, the project head of Upper Myagdikhola-1, said that the transportation of construction materials and equipment has been affected by the floods in Ghumawane, Baloute, Bangepahiro, Ilpu and Shivratri rivers. The construction of the Upper Myagdi project, which has a total of 60 percent physical progress, has been affected. There has been a problem in transporting construction materials due to landslides at various places along the roads of Darkhola and other projects.

However, the production of Upper Rahughat, Mangale-Chimkhola-Rahughat, Upper Bolkhola and Bolkhola hydropower projects in the Rahughat Corridor has been regular. Along with the main structures of the hydropower project, the flood has shown that transmission lines, access roads, construction material storage areas and housing structures are also at risk.

There is a need to make river erosion control, safe embankments, alternative access routes, transmission tower protection and disaster preparedness an integral part of project construction and operation to protect the increased investment in the hydropower sector. Rasas