Bajura. Contracts for two important bridges in Bajura, which have been stalled for years, have been cancelled. After the company entrusted with the construction of the Maure bridge over the Budhiganga river and the Thulisanghu Khola bridge in Badimalika Municipality did not work, the contract was canceled and the construction process was started again.
The construction of both bridges, which were contracted about five years ago, should have been completed within three years. But due to the extreme negligence of the construction company, the work could not proceed until now.
On 11th January 2078, for the construction of Maure Bridge connecting Budhiganga and Triveni Municipalities, Mahakali Bridge Project Mahendranagar signed an agreement with Bikoi Builders Pvt. Although the target was set to complete the construction by February 2081, when the company did not start the work, the planning office canceled the contract and recommended that the company be blacklisted.
The construction company went to court against the decision to cancel the contract. But in July 2083, after the court ruled in favor of the planning office, the process of bridge construction resumed, informed Ravi Shah, Information Officer of the Mahakali Bridge Project.
According to Karna Bahadur Thapa, the head of Triveni municipality, due to the absence of a bridge on the Budhiganga river, the municipality’s transport services are completely disrupted during the rainy season. Even in winter, one has to cross dangerous rivers. He said that if the Maure bridge is constructed, the movement of Badimalika area will be easy.
Similarly, the bridge that was supposed to be built on Thulisanghu river of Badimalika municipality under the Martadi-Ghatmuna road section near the headquarters Martadi has also been stalled for years. On February 10, 2077, a contract was signed with Bikoi Builders Pvt. Ltd. for 16 million 21 million rupees to complete the construction within three years. There was a plan to build a 30 meter long and 11 meter wide concrete bridge over the said river.
Due to the lack of bridge, the citizens of Gaumul, Badimalika and Khaptad Chededah Rural Municipality have been suffering in the movement during the rainy season. Information Officer Shah said that although both the bridges were contracted under the same construction package, the contract had to be canceled after the construction company did not work.
The process has been started through the Nepal Infrastructure Company under the Ministry of Infrastructure Development to proceed with the construction of both the stalled bridges. Earlier, on-site tests were also conducted by deploying technical teams at both the project sites.
In Bajura, not only bridges, but also road construction projects are stuck due to contract agreements. According to Infrastructure Development Office Achham, if the construction company does not work on time, even the allocated budget for road upgrading and black paper cannot be spent and it is returned.
In the last financial year 2082/83, Rs 20 crore allocated for the Martadi-Kolti road and Rs 135 million for the road connecting Martadi via Khaptad-Gairikhad-Atichour were returned. Martadi-Kolti road construction has been done by PS Baniyan Nirman Seva, while KSM KBC/Tej JV, Dhangadhi has taken the responsibility for the construction of the other road.
Due to the delay in the construction of roads and bridges, the daily life of the locals has been affected. In addition to the disruption of transport services, the locals complain that there are difficulties in delivering agricultural products to the market and access to basic services such as health and education.
As development projects are not completed on time, not only the allocated budget is not spent, but the citizens have to suffer for years. There is a need to make the builders accountable, to carry out regular monitoring and to complete the stalled projects with priority.